Sarichioi and Cobadin Wind Farms
EDP Renewables
Sarichioi Wind Farm has installed capacity of 33 MW with 11 Vestas V90 turbines, 3.0MW each and 105 rotor.
The Park's deployment area is 69 ha, where 16,5km of access, 17.000m² of platforms, a 33kV/110kV substation and Control Buildings were built.
The connection to the national network is provided by 110kV OHL with 14km and IN-OUT Station for the national network. Underground line 18/30kV with 43km of extension.
Cobadin Wind Farm has an installed capacity of 26 MW with 13 Vestas V90 turbines, 2.0MW each and rotor 95.
In this wind farm there is a 33/110kV substation and Control Buildings.
They were built of more than 13km of connection links between all the turbines and 13 platforms.
The connection to the national network is ensured by 110kV OHL and IN-OUT Station. Underground line 18/30kV with 72km of extension.
Type:
Infrastructure, Energies
Country:
Romania
Location:
Sarichioi and Cobadin
Start date:
2011
Final date:
2013